Projects -- Shelter House Status
|
Vermont Lutheran Church
|
|
|
Shelter House Status |
| Date | |
| June 27, 2010 | Dedication ceremony. Project complete |
| June 16, 2010 |
Deck, pavers, concrete |
| June 8, 2010 | Mantelpiece and bench finishing in Earl Brandt's shop, kitchen entryway nearing completion, grout being applied to floor tile |
| June 2, 2010 | Laying bricks, tiling, constructing roof over church kitchen entry, starting mantelpiece |
| May 21, 2010 | Doors being glued. Trim being planed, sanded, varnished. Walls plastered. Gas stove in. |
| May 9, 2010 | Shingling started |
| May 3, 2010 | Roof panels installed, fascia and soffits in progress |
| April 22, 2010 | Roof boards installed |
| April 18, 2010 | Walls are up. Timber roof supports are being installed |
| April 8, 2010 | Subfloor tasks completed. Ready for concrete floor to be poured |
| April 5, 2010 | Foundation filled with gravel, leveled, and compacted |
| March 25, 2010 | Footings poured |
| March 23, 2010 | Site preparation begins at Vermont Church |
| March 20, 2010 | Planning luncheon held at Vermont Church to discuss construction plans |
| March 10, 2009 | Timber preparation (sanding, staining, fitting) begins at Herrling Farm |
| October 4, 2009 | Congregation votes (72 to 9) to proceed with shelter house project |
|
|
|
|