Shelter House Construction (March - June, 2010)
June 26 - Volunteer lunch
June 16 - Deck, pavers, concrete
June 8 - Mantelpiece and bench finishing in Earl Brandt's shop, kitchen entryway nearing completion, grout being applied to floor tile
June 2 - Laying bricks, tiling, constructing roof over church kitchen entry, starting mantelpiece
May 21 - Doors being glued. Trim being planed, sanded, varnished. Walls plastered. Gas stove in.
May 9 - Shingling underway
May 3 - Roof panels installed, fascia and soffits in progress
April 22 - Roof boards installed, electrical work
April 18 - Walls and timber roof supports
April 8 - Preparation for pouring of concrete -- installation of plastic sheeting, styrofoam, wire grid, hot water tubing
April 5 - Foundation and fill
March 25, 26 - Forms and footings
March 24- Site preparation begins at the church with the digging of new signpost holes, the removal of the kitchen steps, and grading of the shelter house site.
March 10 - Shelter house construction begins at the Herrling Farm with the sanding and staining of the large imposing rough-cut pine timbers obtained from Northern Illinois and Northern Wisconsin (near Mercer). The timbers are also being cut to length and end-angled so that when transported to the church they will be ready to assemble.
| June 26 | ||
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
||
| June 16 | ||
|
|
||
![]() |
|
|
|
|
|
|
![]() |
|
|
![]() |
![]() |
|
![]() |
![]() |
|
|
|
|
|
|
|
|
|
![]() |
![]() |
|
![]() |
|
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
||
| June 10 | ||
|
|
![]() |
|
![]() |
![]() |
|
|
|
|
|
|
|
||
| June 8 | ||
![]() |
![]() |
|
|
|
![]() |
|
|
|
|
|
![]() |
![]() |
|
|
|
![]() |
|
| June 2 | ||
![]() |
|
|
|
|
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
| May 21 | ||
![]() |
![]() |
|
![]() |
|
|
![]() |
|
|
![]() |
![]() |
|
|
|
||
![]() |
|
|
| May 9 - Shingling underway | ||
![]() |
![]() |
|
| May 3 - Fascia and soffits | ||
![]() |
||
|
|
|
|
| April 22 - Roof boards | ||
![]() |
|
|
![]() |
![]() |
|
![]() |
|
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
||
| April 18 - Walls and roof timbers | ||
![]() |
![]() | |
![]() |
![]() | |
![]() |
| |
|
|
|
|
![]() |
![]() |
|
![]() |
|
|
![]() |
|
|
![]() |
![]() |
|
|
|
![]() |
|
![]() |
![]() |
|
| April 8 - Sub-floor tasks | ||
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
|
|
![]() |
![]() |
|
| April 5 - Foundation fill | ||
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
| March 25, 26 - Forms, footings | ||
![]() |
![]() |
|
![]() |
|
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
||
|
March 24 - New signpost holes |
||
![]() |
![]() |
|
| March 24 - Removing the steps | ||
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
![]() |
|
| March 18 - Preparing the timbers | ||
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
|
|
![]() |
![]() |
|
![]() |
![]() |
|
![]() |
||
| March 10 - Preparing the timbers | ||
|
|
|
|
![]() |
|
|
|
|
|
|
![]() |
|
|
|
|
|
|